How Tilt-Up Construction Works
- Step 1: Perimeter & interior concrete foundations are installed.
- Step 2: Concrete Floor Slab on grade is placed with required reinforcing.
- Step 3: FULLTILT Concrete Wall Panels are formed to size on the concrete slab with required reinforcing and lifting inserts.
- Step 4: All FULLTILT Concrete Wall Panels are cast on site.
- Step 5: FULLTILT Wall Panels are tilted into place with a mobile crane.
- Step 6: All panels are temporarily braced to the floor slab.
- Step 7: Wall Panels are supported by the perimeter concrete foundations.
- Step 8: Structural Steel columns, beams and open webbed steel joists are installed and connected to the FULLTILT Panels.
- Step 9: The Structural Steel Roof Decking is welded into place.
- Step 10: The insulation and roofing membrane are installed. Solar Panels are optional.